This project was Certified on March 19, 2004

Sector

Water / Wastewater

Location

Mission, Texas, USA

Benefited Population

45,400 people

Projected Cost

$3,520,000.00 USD

Sponsor

Hidalgo County Irrigation District#16

ID#

428

The project consists of the upgrading of relift pump stations No. 1 & 2, the re-lining of 5 miles of the existing concrete-lined main canal with a membrane and installation of a computerized pump control system of the Hidalgo County Irrigation District No. 16 (HCID#16) water conveyance system.